Download the Best Curated Project Tools, Templates and PM Emails. Download the Best Curated Project Tools, Templates and PM Emails. Skip to content. Get Full Access Now! Free Resources; Pricing; Log In. Microsoft Project (1) Microsoft Visio (2) Microsoft. Somasundaram, Microsoft Answers Support Engineer. We appreciate your participation in MS Forums, Help us understand your needs better. To share your valuable Feedback please Click here.

How Microsoft Project Works with Project Financial Management

Oracle

Database Template (with EM 13.4.0.0.0 repository pre-configured) for Installing Oracle Enterprise Manager Cloud Control 13c Release 4 (13.4.0.0.0) To know more about how to use these template for installing EM 13.4.0.0.0 refer Enterprise Manager Cloud Control Basic Installation Guide 13c Release 4 (13.4.0.0.0 ) available here. Discover how construction and engineering companies can leverage the cloud to quickly, easily, and inexpensively manage an end-to-end project controls platform that enables the collaborative workflows and communication needed to improve productivity and margins in project management efficiency. Choose from thousands of free Microsoft Office templates for every event or occasion. Jump start your school, work, or family project and save time with a professionally designed Word, Excel, PowerPoint template.

Microsoft Project integration enables project managers to create projects, complete in-depth scheduling using dependencies and constraints, and perform what-if analysis offline before synchronizing project plan and progress information with Project Financial Management applications in Oracle Fusion Project Portfolio Management.

Project executives, project accountants, and billing specialists can use the information exported to Oracle Fusion Project Portfolio Management for financial planning, project costing, billing and revenue accrual, and performance reporting.

The integration of Microsoft Project versions 2007, 2010, 2013, or 2016 for desktop with Project Financial Management applications lets you to do the following:

Installing the Microsoft Project Integration Client

A project manager or project administrator can download and install the integration clients available for different versions of Microsoft Project to integrate with Project Management or Project Financial Management applications.

Before downloading the client, ensure that you have .NET Framework 4.5.2 or later versions installed on your computer. Contact your Help Desk to find the existing .NET Framework version and steps to upgrade it, if needed.

The following table provides the list of available clients and their features.

Client for Project Financial Management ApplicationsSupported Features

Microsoft Project 2007

Scheduling only.

Microsoft Project 2010, 2013, or 2016 for desktop

Scheduling along with support of manual tasks, inactive tasks, free text, and so on.

Note that you can only have one integration client, either for Project Management or Project Financial Management applications, on your desktop. To switch between different clients, you must uninstall the existing client and install the other client.

To install the Microsoft Project Integration client for Project Financial Management applications:

  1. From the Navigator, open Project Financial Management.

  2. From the My Projects page, open the Actions panel tab and select Install Microsoft Project Integration to download the required client.

  3. Save the client, extract the installation files to a local folder, and run the installation file from that folder.

  4. Open the Microsoft Project application and from the Oracle Fusion Projects menu, select Change Environment and enter the URL for Oracle Fusion Applications.

    You can change the environment URL at any time to support subsequent server changes.

Importing Projects

You can import a template or an existing project from Project Financial Management applications to create a new project file in Microsoft Project. During import, select to import all project information or only planning resources. If you want to subsequently export new task assignments for the project to Project Financial Management applications, you must import resources from the primary planning resource breakdown structure.

While importing templates from Project Financial Management applications, you can't select a template that allows changes to the primary planning resource breakdown structure at the project level. This restriction doesn't apply when importing projects.

When importing an existing project, retain the link if you intend to synchronize the project. If you only want to view project details, or intend to export the project to Project Financial Management applications as a different project later, then don't retain the project link. The retain link isn't available if Oracle Fusion Project Management is implemented and you can't retain the project link if third-party scheduling is disabled for the project.

Importing Resources and Rates

Microsoft

You can import all planning resources from the primary planning resource breakdown structure associated with the project in Project Financial Management applications or import selected resources only.

Import rates from Project Financial Management applications to calculate planned costs in Microsoft Project. The Cost Type synchronization option determines whether raw cost rates or burdened cost rates are imported.

Before import, rates are derived for each resource based on the actual or planning rate schedules specified on the associated project plan type. Any override rates you specify on the project plan in Oracle Fusion Project Portfolio Management aren't imported.

Importing Actual Costs and Exporting Progress

You can import actual quantity and costs either from the latest summarized data or from draft progress. The source of actual amounts determines how progress is exported, as described in the following table.

Source of Actual AmountsImpact on Exporting Progress

Latest summarized data

Actual amounts on the draft progress are refreshed from the latest summarized data when you export progress. Also, you specify the progress as-of date in the synchronization options.

Draft progress

Actual amounts on the draft progress aren't refreshed and hence, they match the actual amounts previously imported into Microsoft Project.

When you export progress from Microsoft Project, the estimate-to-complete (ETC) method and physical percent complete calculation method are set to Manual. Values for planned, actual, and estimated finish dates and physical percent complete are exported at each level in the task hierarchy and don't roll up in Project Financial Management applications. Values for all other attributes are transferred at the task assignment level and roll up in Project Financial Management applications.

Download Template Microsoft Project OracleDownload Template Microsoft Project Oracle

After export, draft progress is published. A forecast version is generated depending on progress settings defined for the associated project plan type. You can export progress with raw cost if burdening isn't enabled on the project type. Drupal cache form. If burdening is enabled, then you must use burdened cost to export progress. To achieve this, set the Cost Type synchronization option to Burdened cost.

Exporting Projects from Microsoft Project

You can export a project from Microsoft Project to create a new project in Project Financial Management applications. Exporting links the projects in the two applications. Optionally, set a baseline for the project plan, and simultaneously generate a budget version and create a baseline.

When exporting a project, you must select a source project or template unless you had originally imported a project or template from Project Financial Management applications. The source project or template must allow for third-party scheduling and the associated primary planning resource breakdown structure must not allow changes at the project level.

When exporting projects to Project Financial Management applications, Microsoft Project 2010 or later versions export the tasks based on various conditions as given in the following table.

TasksCondition

Inactive tasks

Doesn't export.

Manual tasks

Exports only if the manual tasks have valid dates and duration.

Manual summary tasks

Exports only if the schedule mode of all summary tasks is automatic. This is because the roll up doesn't happen in Project Financial Management applications.

Synchronizing Project Information

Use synchronization rules to transfer information from and to Microsoft Project. Select the required synchronization rule to synchronize all information, or import or export selected information only. For example, you can select to only synchronize schedule updates for the project. Depending on the synchronization rule, select synchronization options to determine how information is transferred. Also, ensure that you save the changes in Microsoft Project after synchronizing projects to avoid losing your data.

The following table describes the default direction in which attributes are transferred.

AttributesImported into Microsoft ProjectExported from Microsoft Project

Task structure

Yes

Yes

Resources and resource rates

Yes

No

Task attributes

Yes

Yes

Actual quantities and costs

Yes

No

Scheduling and progress

No

Yes

Import Options while Synchronizing Projects

Microsoft Project schedules tasks differently from the Project Financial Management applications. For example, Microsoft Project considers resource availability and tasks dependencies while the Project Financial Management applications don't.

Microsoft Project uses three key attributes to schedule tasks: work, dates, and units. A change to one attribute must be offset by a change to one of the other two attributes. Because Microsoft Projects schedules tasks differently, you can't import work and dates for new task assignments and still have the assignment units as 100%. When you import, you must select which of the three values you want Microsoft Project to calculate and the remaining two values are imported.

For example, assume you import a new task assignment with the following attributes:

Download template microsoft project oracle tutorial

The new task assignments are imported as explained in the following table based on the option selected during synchronization:

OptionExample Calculation

Calculate Dates

With the start date as 03-Aug-15, the work as 16 hours, and the units as 100%, Microsoft Project calculates the finish date as 04-Aug-15.

Calculate Work

With the start date as 03-Aug-15, the finish date as 03-Aug-15, and the units as 100%, Microsoft Project calculates the work as 8 hours.

Calculate Units in Microsoft Project 2007 or Peak in Microsoft Project 2010 and later versions

With the start date as 03-Aug-15, the finish date as 03-Aug-15, and the work as 16 hours, Microsoft Project calculates the units or Peak as 200%.

How Enterprise Performance Management Works with Project Management

You can integrate Enterprise Performance Management (EPM Planning) and Project Management to perform organizational planning and budgeting and to execute projects. With this integration, you can manage projects without any delays, duplication of effort, or manual budget validation.

Here's how the integration handles the projects.

Integration Settings

You use Data Integration to drive the data between the two products. EPM Planning Data Integration enables to apply predefined mappings from the Project Management data model to target dimensions.

Following are the settings required for the integration on the EPM Planning side.

Integration Considerations

To export a project and project budget from EPM Planning to Project Management, the project status in EPM Planning must be Approved and the project integration status must be Initial (not yet sent to Project Management) or Ready (already sent to Project Management and can be sent again in case of changes).

Integration supports only:

Download Template Microsoft Project Oracle Cloud